Excavation of the second corridor has been ongoing since February this year. While the tunnel boring on the north side is proceeding according to plan, the one on the south side had to be stopped on June 23 after about 190 metres.
A partially unstable rock mass, characterised by fractures and cavities, made mechanical drilling ‘very difficult and challenging’ for the next 500 metres or so.
According to FEDRO, the excavation work with blasting will take about six to eight months. All other work on the north and south sides is proceeding according to plan. Despite the geological setback, the opening date of 2030 for the second tunnel should be met. The overall budget of the work is around CHF2.14 billion.
In order to ensure that the timetable is met, various measures will be implemented: for example, some critical work will be carried out earlier than planned. Blasting on the approximately 500-metre section will be carried out uninterruptedly, in continuous shifts, seven days a week, it is still specified.
More
More
Milestone reached in Swiss Gotthard tunnel extension
This content was published on
Two large tunnel boring machines have begun excavating the second corridor of the Gotthard road tunnel.
We select the most relevant news for an international audience and use automatic translation tools to translate them into English. A journalist then reviews the translation for clarity and accuracy before publication.
Providing you with automatically translated news gives us the time to write more in-depth articles. The news stories we select have been written and carefully fact-checked by an external editorial team from news agencies such as Bloomberg or Keystone.
If you have any questions about how we work, write to us at english@swissinfo.ch
Popular Stories
More
Climate adaptation
Why Switzerland is among the ten fastest-warming countries in the world
Euro 2025: Bern prepares for massive parade ahead of Switzerland-Spain game
This content was published on
The last Euro 2025 match to be played in Bern, the quarterfinal between Spain and Switzerland at 9pm on Friday, promises to be a great celebration of football.
Clariant faces further ethylene price-fixing claim
This content was published on
Swiss chemicals group Clariant is facing a further claim for damages in connection with ethylene price-fixing agreements.
This content was published on
The Grande Dixence dam in Lower Valais is closed to visitors due to a rockfall last weekend. The nearby hotel also had to temporarily suspend operations for safety reasons.
You can find an overview of ongoing debates with our journalists here . Please join us!
If you want to start a conversation about a topic raised in this article or want to report factual errors, email us at english@swissinfo.ch.